Fox Technical Operations Center

Project Details

Date: 1999 and remodel in 2014

Location: Century City, CA.

Size: 285,000 s.f.

Attributes: Prefab, Preconstruction, Lighting Control,

Share Project

This project consisted of the original 5 story聽building聽that houses Fox Digital offices, 41 audio edit rooms, two 10,000 s.f. digital broadcast sound stages and associated support facilities.聽 It聽was the first digital sound stage built for on-air broadcasting.聽 麻豆果冻传媒影音 furnished and installed high voltage switchgear (redundant feeds from DWP), two 1750 kVA emergency generators, paralleling switchboard with capacity for a third, UPS system, grounding system, installation of owner furnished theatrical dimming systems, TVSS equipment and associated work.聽 The electrical and low voltage systems were designed to ensure Fox would remain on air in the event of a power outage event.聽聽 The recently remodeled 5th Floor VIP office space and聽Technical Operations Center spaces are the very heart of Fox Networks’ Sports programming operations.